You can create many reports from the jobs module > jobs list simply by changing the jobs list view field. Job list #13 can be used for getting a broad summary of your project health by dimension. All job enabled dimensions can be added to the grid.

ON THIS PAGE YOU WILL FIND:


HOW TO RUN JOB LIST 13

  • Go to the jobs module > jobs list > filter your jobs list according to what you want to see in your report e.g. client/client group and project

  • Click apply

  • Once the job list has been filtered change the job list to status report (13)

  • Your job list will reformat to WorkBook’s status report (2)


EXPLANATION OF JOB LIST 2 DETAILS

There are a number of columns that can make up job list 2 - here is a break down of the column headers and their definitions.

COLUMN NAME/S

DEFINITION

Client

The client the job belongs to

Project

The grouping, campaign or project this job belongs to. It comes from the Project field in the job properties sidebar

Job No.

WorkBook job number

Job Name

Indicates the name of the job

Created

Date the job was created

Start Date

Indicates the start date of the job. It comes from the Start Date field in the job properties side bar

This is usually the same as the creation date unless it has been manually changed in the job properties side bar

Delivery Date

Indicates the delivery date of the job. Comes from the Delivery field in the job properties sidebar

End Date

Indicates the job’s end date. It comes from the End Date field in the job properties sidebar

Status

Is a free text field where you can write notes on the current status of the job

Production Status

Comes from the Production Status field in the job properties sidebar

Production Statuses need to be setup in advance by a system administrator in Settings > Projects & Jobs

Next Step

Comes from the Next Step field in the job properties sidebar

Next Step Date

Comes from the Next Step Date field in the job properties sidebar

Internal Note

Comes from the Internal Note field in the job properties sidebar

Manager

Comes from the Project Manager field in the job properties sidebar

Client Contact

Comes from the Client Contact field in the job properties sidebar

Quoted

Total value of all Price Quotes on the job (except for canceled Price Quote)

Expenses

Total sales value of time logged to date + any creditor invoices registered to the job + any unsettled POs

Price TO Progress

Expenses divided by Quoted multiplied by 100 and shown as a percentage

Schedule Progress

Total number of hours logged via timesheets divided by the total number of hours that has been scheduled multiplied by 100 and shown as a percentage

Evaluated Progress

Allows you to add in your own percentage on how far you think you are through the job

Public

Allows you to include/exclude jobs on Status Report (10) or Status Report with Gantt Chart (180) - a tick in the check box means it will appear on the report

Type

Comes from the Job Type field in the job properties sidebar

Company

The WorkBook company the job belongs to

Tags

Shows the tags that have been assigned to the job. It comes from the Tags field in the job properties sidebar

Last review

Comes from the Last Review field in the job properties sidebar

Client PO no.

Comes from the client PO number field in the job properties sidebar

Display Currency

The displayed currency of the current user

All the other currencies created/incurred on the job will be converted into the user’s displayed currency using the rate defined under the exchange rate tables.

This is only for displaying purpose. WorkBook still maintain the original currency value set on the transaction.

Code 01, Code 02, Code 03,
Code 04, Code 05

If you need additional fields in your status report, you can add 5 new text fields using these codes and system variable 1052 allows you to create names for these fields

Costing Code

Costing Codes need to be setup in advance by a system administrator in Settings > Costing Code


CONFIGURING JOB LIST 2

Job list 2 contains many details for your retainer reporting purposes. Use the modify grid functionality to configure job list 2 to suit your agency’s retainer reporting process.

For more information on how to use the modify grid functionality refer to the grid view reporting article.


EXPORTING JOB LIST 2

You can export job list 2 to create your own reports using WorkBook’s export grid data functionality.

For more information on how to use the export grid data functionality refer to the grid view reporting article.