Job schedules in WorkBook can be set to ‘Active’ or ‘Inactive’ via the Tasks > Settings tab. The ‘Schedule is active’ box is checked by default. 

...

...

ON THIS PAGE YOU WILL FIND

Table of Contents
outlinetrue

...

OVERVIEW

When a ‘Schedule ‘schedule is active’: 

  • Bookings will appear in a resource’s Task task list

  • Bookings will appear in capacity planning views

...

Once a schedule is built, the ‘Schedule ‘schedule is active’ box can be unchecked and the status will change to ‘inactive’, this means:

  • Bookings are not visible to a resource in their Task task list

  • An activation probability % can be set on inactive schedules

  • Inactive schedules can be viewed by probability in the:

    • Scheduling module >

    Weekly Schedule
    • weekly schedule and

    • Scheduling module >

    Task
    • task matrix views (

    color
    • colour coded to purple)

  • In the drop-down menu, brackets around the schedule name indicate that it is inactive

...

USING AN INACTIVE SCHEDULE FOR CAPACITY PLANNING

Create an inactive schedule

  • Create the schedule , > add phases and tasks , > and add resources (but don’t - do not book hours yet).

  • Go to the schedule’s Settingssettings tab > Uncheck ‘Schedule uncheck ‘schedule is active’ and  > set the Activation activation probability %

...

  • To book hours, go to the Taskstasks tab and > open the Booked Resourcesbooked resources horizontal panel, enter

  • Enter hours against each resource via the List list view > Bookingbooking column

...

...

CAPACITY PLANNING VIEWS

To see how inactive schedules impact capacity, go to the 

...

scheduling module > 

...

weekly schedule or 

...

task matrix views.

...

Notes: 

...

  • A schedule must be ‘active’ to add/edit resources on tasks but can be ‘inactive’ to book hours

...

...

  • Only automatic bookings according to the schedule or task setting can be used on inactive schedules, i.e.

...

  • ‘even distribution of hours’ or

...

  • ‘first available capacity’

...

...

  • Manual bookings are NOT displayed in capacity planning views in current versions

...

  • of WorkBook

Weekly Schedule

In 

...

scheduling > 

...

weekly schedule we can review total hours booked per resource on both active schedules and

...

 inactive schedules. This view allows you to:

  • View booked hours, % or revenue, or available capacity against a resource by day, week or month 

  • See the planned resource capacity for active schedules across jobs

  • See the planned resource weighted for inactive schedules by the activation probability %

...

Task Matrix

In 

...

scheduling > 

...

task matrix we can review resources and see the jobs and tasks they have been booked on in both active schedules and inactive schedules. This view allows you to:

  • View booked by number of hours or revenue by day, week or month 

  • See the planned resource capacity for active schedules across jobs

  • See the planned resource weighted for inactive schedules by the activation probability %

...

Re-schedule and edit hours on ‘active’ schedules only

...

...

View Inactive Schedules

To view data in either of these views

...

:

  • Click on the Filter icon (blue star) to adjust the data set you are viewing:

    • Period by entering a start date > select to view data by Week / Month > select the time period in Days / Weeks / Months

    • Update Resource resource filter to include your company, resources or teams 

    • Check ‘Include ‘include inactive schedules’ box and the relevant option for how you would like to view capacity across inactive schedules:

      • Check Use existing estimateuse schedule probability to represent the Activation activation probability as per the % applied on each individual schedule OR,OR…

      • Check the % slider to apply one percentage across all inactive schedules, i.e. this could be set to 100% to view potential future capacity across all jobs should they all be approved.

...

Info

Colour coding within cells alerts you to capacity issues:

  • Purple = Booked on inactive schedules (according to the probability % option selected in your Filter settings)

  • Yellow = Booked on jobs in Quotation status

  • Green = Booked on jobs In progress

  • Red = Overbooked

...